Congratulations to York County Natural Gas Authority and Laurens Commission of Public Works for being awarded a PHMSA Natural Gas Distribution Infrastructure Safety and Modernization Grant!
This is a huge honor and we are so proud of these two CPGA members!
Below are the two member's grant initiatives.
Laurens Commission of Public Works: The goal is to replace 8 miles of main and 717 steel services with PE pipe. The existing pipelines consist of pre-code steel and bare steel. The applicant also proposes to replace approximately 0.22 miles of pre-code 8-inch highpressure distribution pipeline with new modern coated steel.
York County Natural Gas Authority: The goal is to replace approximately 13.6 miles of steel and Driscopipe and Chevon plastic pipe with steel and PE pipe. The existing piping was installed over 70 years ago.